ProjectTaco Town — Northpark
BrandTaco Town
Address850 Northpark Dr, Suite 12, Dallas, TX
Status Completed
Square Footage2400
Start DateNov 01, 2025
End DateMar 15, 2026
Hrs/Sq Ft0.10
240.0
Total Man-Hours
32
Total Workers
8
Days Worked
8
Labor Entries
Man-Hours by Trade
Trade Entries Workers Man-Hours % of Total
Framing 1 6 48.0 20%
Demolition 1 5 40.0 17%
Painting 1 5 40.0 17%
Electrical 1 4 32.0 13%
Flooring 1 4 32.0 13%
Plumbing 1 3 24.0 10%
Final Cleaning 1 3 12.0 5%
Punch List 1 2 12.0 5%
Total 8 32 240.0 100%
Full Labor Log
Date Trade Subcontractor Workers Hrs/Worker Man-Hours Description
Nov 05, 2025 Demolition Ace Demolition LLC 5 8.00 40.0 Demolition work on November 05, 2025.
Nov 12, 2025 Framing ProFrame Builders 6 8.00 48.0 Framing work on November 12, 2025.
Dec 01, 2025 Electrical Bright Spark Electric 4 8.00 32.0 Electrical work on December 01, 2025.
Dec 10, 2025 Plumbing FlowRight Plumbing 3 8.00 24.0 Plumbing work on December 10, 2025.
Jan 05, 2026 Painting ColorPro Painting 5 8.00 40.0 Painting work on January 05, 2026.
Jan 20, 2026 Flooring TopFloor Flooring 4 8.00 32.0 Flooring work on January 20, 2026.
Feb 10, 2026 Final Cleaning CleanSweep Services 3 4.00 12.0 Final Cleaning work on February 10, 2026.
Mar 01, 2026 Punch List ProFrame Builders 2 6.00 12.0 Punch List work on March 01, 2026.